Wed Jul 18, 2012 | Post #1 | S L Gupta (Civil Engg)
Join date: Mar 2008 | Dear Ankur
You want cement concrete i.e. RCC wall 200'x35'x3'' =1750 cft and the rate per cft is RS 250-00 per cft which comes Rs 6 3 -00per sft. and M. S. steel cost is Rs 120-00 percft or Rs 30-00 per sft. | |
|
Thu Jul 19, 2012 | Post #2 | Ankur Kothari
Join date: Jan 2012 | THANK YOU SIR | |
|
Fri Jul 20, 2012 | Post #3 | sam_m400
Join date: Jul 2012 | Post subject: Cost of concrete walls
Why measured in Cu:ft and Sq;ft ? Which rate we should take in finding the total calcuation?
I have seen some contractors saying foundation will be on Cub:ft , but some saying it is on Sq:ft .How do we judge which is on Cub;ft and which is on Sq:ft
| |
|
Fri Jul 20, 2012 | Post #4 | Ar. Manoj Ralen
Join date: Feb 2008 | Dear Sam, All construction work has three dimensions which is length, breadth and height/depth so it makes sense to have these in cubic feet. However for some of the work, where one dimension is standard you can measure that work in square feet. For example, if you are doing a brick work for 9inch wall then you can measure the wall area in square feet because the thickness has been fixed. It is a good practice to clearly understand all three dimensions while negotiating a price with the contractor.
Let me know if you need more information. | |
|
|