Construction Stories
All channels Construction Stories Consequences of not marking Layout ....
Construction Stories
Construction Stories
Love them or leave them; but these real life incidents have a lot to teach us about the construction techniques and the problems that may occur if these are not followed properly.

S L Gupta (Civil Engg)
By S L Gupta (Civil Engg)
I am a civil engineering expert and I have been in the construction industry for almost 40 years. I have seen the industry grow from manual to hi-tech work techniques and currently I am working as a c...
Read more>>
Consequences of not marking Layout of building, Layout of building Consequences of not marking Layout of building before starting construction work
  By:S L Gupta - On Monday, August 31,2009  -  15309 View(s)  -  8 Comment(s)
Consequences of not marking Layout of building, Layout of building 

Here I am highlighting one glaring incident that took place due to not marking “LAYOUT” of building properly before starting construction work. It is an important aspect of construction work. The slackness made in layout causes extensively damage to the work and heavy loss to the owner.

All this happened due to ignorance, negligence and desire to save money by not marking centre line, base line and not constructing marking pillars or BURJI indicating prominent axes of the building’s walls and columns. These BURJIS act as reference points for laying out any parts of building in later. This episode is being cited to caution owners of the building, contractor, supervisor of contractor and architect responsible for supervision.

In November, 2007 I visited a site of hospital building with my friend; which was under construction at Sonepat. I was stunned to see that some laborers were dismantling RCC columns by mechanical means and rectifying M.S. steel bars of columns. These columns were constructed up to 2 to 4 feet high from plinth level. I enquired of dismantling work from the owner of hospital. The owner told us that he has let out the work on labor rate to contractor and has hired a local architect for supervision of work also.

Ignorant Owner & No Technical Help
The owner also told that he doesn’t know about construction work and totally depends on the contractor. He told us that one day my relative who is engineer came here and after visiting the site he told me that the alignment of columns were incorrect and with incorrect alignment it is not possible to construct a building.  The owner said that he called contractor, architect and his relative engineer to show them all irregularities by using tools like SUTTA, plumb bob, try square and straight edge etc. Both the contractor and architect showed their inability to correct the alignment and left the work.

Mistakes got punished gravely
It is certain that nature does not spare anyone if the things are not done properly. It doesn’t matter if the person committing the fault is ignorant or negligent nor does it matter about the honesty, integrity and knowledge of the people involved.

The contractor started the work in unplanned manner. He did not construct marking pillars, BURJIS, not fixed base line and centre line. He started excavation work of columns, walls one by one without checking their distances and alignments and laid the lean concrete. After that he erected M.S. steel bars of columns without taking any respective distances and centre line references from either front row or middle row or back row of columns. By doing the work in hazardous manner some R.C.C. columns constructed out of line and resulted into heavy loss.

The owner further told that he arranged another contractor for construction work. The new contractor started the work after rectifying the defects but rectification of steel bars by buckling reduced the strength of R.C.C. columns.

The owner told that he faced the loss in many counts i.e. cost of dismantling, material and labor cost for re-construction and wastage of time and the project took 3 months more time for completion. This delay also caused him loss due to late functioning of the hospital.



How it happened?
The hospital building had nearly 10,000 sq. feet area and the contractor and his mason did some mistakes either knowingly to save money or due to ignorance. The architect deployed a local man who knew only job of making drawings but had no experience of construction work in the field. He did not measure or check any thing himself but left all this for contractor.

1. In fact the contractor constructed small houses and had no experience of making frame structure building.
2. He started the work in unplanned manner i.e. he did not construct marking pillars, BURJIS and did not fix base line and centre line.
3. He started excavation work of columns, walls one by one without checking their distances and alignments and laid lean concrete.
4. After that he erected M.S. steel bars of columns without taking any respective distances and centre line references from either front row or middle row or back row of columns.
5. After erecting M.S. steel bars of columns, the contractor started laying cement concrete in footings of columns and filled columns up to 2 to 4 feet from plinth level.
6. When error came to notice, the contractor filled many columns 2 to 4 feet from plinth level.

Why it happened?
The incident happened due to ignorance of layout and not following demarcation procedure.

1. Construction work started without doing layout/demarcation.
2. Unskilled and inexperienced masons who did not know the job well were employed to do work.
3. Due to carelessness from owner, the contractor, masons and supervisor thought that nothing would happen as it was routine work.  



What precautions should have taken?
The episode happened due to not adopting LAYOUT procedure and precautions for laying foundation.

1. For layout of a building baseline is marked on the ground either from centre line of the road or from any permanent building nearby. This line helps to mark out the front of a building. Side baseline is also marked with the help of side structure or road or it can be marked with the help of first baseline or boundary of the plot.
2. Fix temporary pegs at centre line of walls/columns on both sides of walls and columns in front and backside.    
3. Fix pegs at the centre line of walls/columns on both sides of wall and columns in left and right side at the front of building.
4. Check diagonals of the square or rectangle formed after fixing pegs.
5. Construct BURJI or marking pillars with pegs at a distance of 1.5 meter to 2 meters and their top surface should be plastered.
6. Mark centre line on the top of BURJIS with the help of thread (Soot) or with the THEDOLITE in big projects and diagonal and other dimension should be checked.
7. Construct level BURJI on all corners of the building and fix proposed plinth level on the top of BURJI.
8. Mark the foundation of walls/columns according to drawing on the ground with the help of centerline marked on BURJI.
9. Mark foundation trenches on the ground with chalk powder.
10. Excavate the foundation of walls /columns up to required level and the excavation must be checked with the help of centre line and level BURJI to avoid any complication in later.
11. After erecting M.S. steel bars, centre line should be checked again.
12. It is also necessary to check outer lines of columns at the time of filling cement concrete in formwork.

 
Did you enjoy this post? Please share it!
DiggRedditDel.icio.usGoogleLiveFacebookSlashdotNetscapeTechnoratiStumbleuponSpurlFurlBlogmarksYahooPlugimSquidooBlinkBits
8 Comment(s)
By gnyoganarasimhan : On Friday, January 31,2014
This happened a few days back.One of close relative wanted to construct a dhyana mandira about 40kms from Bangalore where I stay.He had engaged a labour contractor and another civil engineer to occasionally over see they work.Before starting the work he had also taken me along with him.It is a octagonal shaped building designed by the architect and a combination of RCC and structural steel work.I advised them to first construct small pillars for center line marking of walls and columns.Being a odd size building it was required to erect 44pillars for center line marking.
I gave them the example of sharpening the axe is very important before cutting as otherwise a dumb axe will take more time to cut and it may also be improper while a well sharpened axe will cut in one stroke and also properly.In other words it is better to take more time for better planning than starting the work without proper planning.Unfortunately they did not listen to my word and the labour contractor with some vague marking started the excavation work.After some days I was asked to accompany my relative to the construction site.When we went there I noticed that they were laying footing concrete.Just before coming back I went near the concreting place and I noticed that column was not placed at the center.I immediately told my relative that there appears to be something wrong in the marking.On further request ,I went into details and to my horror it was noticed that many footings were not marked properly and a few column footing concreting was also done.The concreting was stopped immediately and it took nearly one week to rectify the problem.Due to this rework the owner lost not only time but also rs35000/- in rework(material cost).The labour contractor also suffered extra expenditure towards labour.
This is purely because of not marking properly by avoiding expenditure towards erection of centerline pillars.
 
By sunil : On Monday, June 20,2011
It is a very good article. I too faced a similar situation. I had given turnkey project for my 3 storied house to Dutta & Dutta Architects of Chandigarh.
They did a very shabby job and deployed cheap and inexperienced sub contractors for mason, plumbing, electrical & wood work jobs. They changed most of these sub contractors in between or rather the sub contractors left the job due to non payment of timely payments by Mr Dutta. I WAS NOT ABLE TO monitor much because of posting in a different city. A lot of glaring mistakes were observed later. Also, material used by these turnkey people is of poor quality. They try to save even small-small amounts, where ever they can. e.g they use lower thckness/ width of wood for door/ window frames or use use higher Qty of sand for plastering. And U cannot monitor everything. A turnkey project is given to avoid the botheration or by people with no knowledge. But ultimately it is Ur project and your own involvement at each step is essential. These contractors/ subcontractors are interested only in their payments and that too as early as possible. My advice is that in case of turnkey project also, checkout the work of the subcontractors deployed yourself before allowing contractor to use them for Ur site. Ask the owners of previous sites about the work done, faults, etc. Also, don't don't come under pressure and give payments as demanded.
Make a very-very detailed agreement with the contractor. Try to put as many details/ specifications as possible and don't sign a general type of 1-2 page agreement.
Add clause of penalty for delay in completion because delay will also also result in higher construction costs besides other losses.
 
By Anil : On Saturday, June 18,2011
A Very good article providing basic information regarding layout of the building before construction.Quite useful for a house owner having little knowledge of basic construction facts to be folloowed.
 
By Anubhav Singh : On Monday, March 7,2011
Hello Mr. S.L. Gupta,

I am planning to construct 2 floor bulding of area 60 sq yds (17.9" face width X 30.2" length) of east facing. I want to build 1 room set (1 room, kitchen & bathroom) and a parking area at ground floor. In second floor, there will be a bedroom, living room and dining room cum open kitchen. I need to know, what would be the construction cost?

Thanks,
Anubhav Singh
 
By D K BHATNAGAR : On Sunday, January 30,2011
good article
 
By Preetam : On Friday, December 31,2010
This is a very good article(information) for any prospective house owner. Most of the people lack the basic idea of making frame structure buildings and are at the mercy of the contractors. This information will help them to start their project with some level of knowledge. Gharexpert.com and experienced people like yourself will always be there to guide them with more tricky problems. KEEP UP THE GOOD WORK. You are really a boon to the new home owner community !!!
 
By vandana jain : On Monday, August 16,2010
NICE AND INFORMATIVE INFORMATION ..THANK U SIR
 
By Aswini kumar sahu : On Friday, October 23,2009
quite useful
  Add Comments/Feedback
  *Your name  *Email address
 
  *Comments/Feedback
(Max 4000 characters.)
Click here for ceiling design in trend
Featured article
kitchen design; Smart, usable or beautiful, take your pick
kitchen design; Smart, usable or beautiful, take your pick
So what would you choose when you have to go for a kitchen design. Should it be smart, should it be usable or should it ...
Read more Read more

Tile Flooring, Designs and Installation Guidelines
Tile Flooring, Designs and Installation Guidelines
One of the fastest growing trends in the flooring, tiles come in a wide variety of styles, patterns and colors.
Read more Read more

Purchasing Guidelines for Timber
Purchasing Guidelines for Timber
Timber should be of first grade and be free from decay, fungal growth, boxed heart, pitch pocket or streaks on the split
Read more Read more
View all View all articles
Popular Channels
www.mahto.co.in
www.mahto.co.in
Dial 07428251217 & 09990641559 for your Interior, Exterior & Event Solution. (India) e-mail: delhi@mahto.co.in with your inquiries. (Time in 24 x 7) or www.mahto.co.in
Generate
Generate more business through GharExpert.com
Now you can officially generate more business from GharExpert.com. Here are the steps you can use to generate business
New
New Picture Gallery at GharExpert has Social Discovery built into it
GharExpert Picture Gallery is now better than ever before. It now has social discovery feature built into it and brings to you more exciting designs that the world is finding on the website. Every hour will see new designs on the website
View all>>

Your ad here
Copyright 2007- GharExpert.com All rights reserved.  

 
 |  Advertize with us  |  About us  |  Contact us  |  RSS  |  Blog  |  Terms of service  |  Style made simple  |  Decorating slide show  |  Tips  |  Give your feedback  |