There are following initial steps to be taken for laying the foundation.1: Clearance of site2 Layout of the building3 Excavation in foundation4 Laying cement concrete in foundation5 Laying brick work in foundation6 Laying mild steel and cement concrete for footing of RCC column7 Laying 40 mm thick horizontal DPC
For more details read articles in the section “Start Construction” available at link: http://www.gharexpert.com/category/1326/Start-Construction-0.aspx?PL=2&CatID=1326&Category=Getting%20Started&Page_Id=1: