Question details | |
|
|
| what will be the cost to construct a double store building in 150 yards
Price : Rs.0 Paid : Rs.0 Balance : Rs.0 Question category : Layout and House Plans On : 06/05/2008 Views : 4802 Status : Answered Files attached : No files Expert(s) chosen: S L Gupta |
| |
|
| |
| |
|
Status history |
|
| | Comment by chandra shekhar on Sat Aug 16, 2008 2:05 AM | | Hi Gupta,
I am Chandra Shekhar from Bangalore.
you can call me Chandra.
I am planning to construct a 18 Square house in 40x60 south facing site.
Here is the details
Two House on ground floor one is adjacent to the other.
First one two bedroom house
Second one also two bedroom house
one stairs outside the building adjacent to first house
one staircase inside second house for duplex construction.
vitrified tiles for both house
2 teak wood doors
4 Hard wood doors for all the 4 bedrooms
Total 3 toilet ( 1 each inside the house and 1 common outside the house )
2 kitchens
2 external doors of Hardwood
So total Teak wood door = 2
Total other doors = 4+3+2 = 9
All window are from Hard wood
Total Door frames running feet = 42 sq feet
other wood area runnig feet = 200
Teak wood door shutter area = 49 sq feet
Other wood door area = 210 sq feet
Total window frame running feet = 154 sq feet
Total Window shutters area = 120
Please let me know the estimates
I live in Bangalore.
Please let know the cost for Mumbai city.
|
|
|
|
| | Comment by smriti jain on Sun Jul 20, 2008 2:52 PM | | why do not you just use this free online home construction cost estimator ........ just an idea |
|
|
|
| | Comment by Munish Bansal on Tue Jun 17, 2008 8:05 PM | | Its will be approx 2600 Sq, ft .
So the cost for normal finshed set will be from Rs700 per sq. ft to Rs1100 per sq.ft approx..
Hence cost varies from Rs 18,00,000/- to Rs, 28,00,000/- depending upon type of construction. |
|
|
|
| | Answer updated by S L Gupta on Tue Jun 10, 2008 1:49 PM | |
The area given by your good self is 150 sq. yards or 1350 Sq. feet. You want to construct double storey house but did not mention the area for second storey or first floor level.
Considering area of second storey 90 % of the ground floor area that is equal to 1215 sq. feet, the total area will be equal to 1350 +1215 = 2565 sq. feet. The cost of construction of a house depends on the specification used for construction work.
Tentative estimated cost is:
S.No. |
Nature of work |
Amount in Rupees |
1 |
Earth work Excavation in foundation & earth filling under floor |
41,040 |
2 |
Cement concrete in foundation 1:8:16 |
47,787 |
3 |
Brick work in cement mortar 1:6 in foundation work |
45,015 |
4 |
D P C |
14,765 |
5 |
Brick work in cement mortar 1:6 in super structure |
1,07,152 |
6 |
Tile tracing in roof |
52,639 |
7 |
Rain water pipe |
12,826 |
8 |
RCC without steel in ratio of 1:2:4 |
1,73,933 |
9 |
M S Steel for RCC |
2,17,512 |
10 |
Makrana dungri stone flooring |
1,99,974 |
11 |
Plastering on ceiling |
14,596 |
12 |
Plastering on walls |
31,679 |
13 |
Cement pointing |
9,029 |
14 |
Glaze tiles on walls in bathroom and Kitchen |
70,568 |
15 |
Hard wood frame for door and windows |
1,01,574 |
16 |
Hard wood door shutters |
81,181 |
17 |
Hard wood window shutters |
40,395 |
18 |
Hard wood cupboard box type |
66,918 |
19 |
Iron grills |
28,915 |
20 |
Painting or spirit polishing on wood work |
15,903 |
21 |
White washing on ceiling |
3,771 |
22 |
Oil bond distemper on walls |
56,020 |
23 |
Snowcem for exterior walls |
6,413 |
|
Total Rs. |
14, 38,910 |
|
Electrical fittings including wiring @ 10% of total cost |
1,43,891 |
|
Water Supply & sanitary fitting @10% of total cost |
1,43,891 |
|
Sewerage @ 5% of total cost |
71,946 |
|
Grand Total |
17,98,638 |
Note: In this estimate we have taken general specification of construction work, however, if you want to change the specification by providing good quality marble floor or ceramic tile floor, Teakwood in door and windows, the cost will increase and you can find estimated cost by using cost estimator given at the link below.
Cost Estimator>>
|
|
| | Files attached : No files |
|
|
|
| | Answer updated by S L Gupta on Tue Jun 10, 2008 1:47 PM | |
The area given by your good self is 150 sq. yards or 1350 Sq. feet. You want to construct double storey house but did not mention the area for second storey or first floor level.
Considering area of second storey 90 % of the ground floor area that is equal to 1215 sq. feet, the total area will be equal to 1350 +1215 = 2565 sq. feet. The cost of construction of a house depends on the specification used for construction work.
Tentative estimated cost is:
S.No. |
Nature of work |
Amount in Rupees |
1 |
Earth work Excavation in foundation & earth filling under floor |
41,040 |
2 |
Cement concrete in foundation 1:8:16 |
47,787 |
3 |
Brick work in cement mortar 1:6 in foundation work |
45,015 |
4 |
D P C |
14,765 |
5 |
Brick work in cement mortar 1:6 in super structure |
1,07,152 |
6 |
Tile tracing in roof |
52,639 |
7 |
Rain water pipe |
12,826 |
8 |
RCC without steel in ratio of 1:2:4 |
1,73,933 |
9 |
M S Steel for RCC |
2,17,512 |
10 |
Makrana dungri stone flooring |
1,99,974 |
11 |
Plastering on ceiling |
14,596 |
12 |
Plastering on walls |
31,679 |
13 |
Cement pointing |
9,029 |
14 |
Glaze tiles on walls in bathroom and Kitchen |
70,568 |
15 |
Hard wood frame for door and windows |
1,01,574 |
16 |
Hard wood door shutters |
81,181 |
17 |
Hard wood window shutters |
40,395 |
18 |
Hard wood cupboard box type |
66,918 |
19 |
Iron grills |
28,915 |
20 |
Painting or spirit polishing on wood work |
15,903 |
21 |
White washing on ceiling |
3,771 |
22 |
Oil bond distemper on walls |
56,020 |
23 |
Snowcem for exterior walls |
6,413 |
|
Total Rs. |
14, 38,910 |
|
Electrical fittings including wiring @ 10% of total cost |
1,43,891 |
|
Water Supply & sanitary fitting @10% of total cost |
1,43,891 |
|
Sewerage @ 5% of total cost |
71,946 |
|
Grand Total |
17,98,638 |
Note: In this estimate we have taken general specification of construction work, however, if you want to change the specification by providing good quality marble floor or ceramic tile floor, Teakwood in door and windows, the cost will increase and you can find estimated cost by using cost estimator given at the link below.
Cost Estimator>>
|
|
| | Files attached : No files |
|
|
|
| | Answer updated by S L Gupta on Tue Jun 10, 2008 1:44 PM | |
The area given by your good self is 150 sq. yards or 1350 Sq. feet. You want to construct double storey house but did not mention the area for second storey or first floor level.
Considering area of second storey 90 % of the ground floor area that is equal to 1215 sq. feet, the total area will be equal to 1350 +1215 = 2565 sq. feet. The cost of construction of a house depends on the specification used for construction work.
Tentative estimated cost is:
S.No. |
Nature of work |
Amount in Rupees |
1 |
Earth work Excavation in foundation & earth filling under floor |
41,040 |
2 |
Cement concrete in foundation 1:8:16 |
47,787 |
3 |
Brick work in cement mortar 1:6 in foundation work |
45,015 |
4 |
D P C |
14,765 |
5 |
Brick work in cement mortar 1:6 in super structure |
1,07,152 |
6 |
Tile tracing in roof |
52,639 |
7 |
Rain water pipe |
12,826 |
8 |
RCC without steel in ratio of 1:2:4 |
1,73,933 |
9 |
M S Steel for RCC |
2,17,512 |
10 |
Makrana dungri stone flooring |
1,99,974 |
11 |
Plastering on ceiling |
14,596 |
12 |
Plastering on walls |
31,679 |
13 |
Cement pointing |
9,029 |
14 |
Glaze tiles on walls in bathroom and Kitchen |
70,568 |
15 |
Hard wood frame for door and windows |
1,01,574 |
16 |
Hard wood door shutters |
81,181 |
17 |
Hard wood window shutters |
40,395 |
18 |
Hard wood cupboard box type |
66,918 |
19 |
Iron grills |
28,915 |
20 |
Painting or spirit polishing on wood work |
15,903 |
21 |
White washing on ceiling |
3,771 |
22 |
Oil bond distemper on walls |
56,020 |
23 |
Snowcem for exterior walls |
6,413 |
|
Total Rs. |
14, 38,910 |
|
Electrical fittings including wiring @ 10% of total cost |
1,43,891 |
|
Water Supply & sanitary fitting @10% of total cost |
1,43,891 |
|
Sewerage @ 5% of total cost |
71,946 |
|
Grand Total |
17,98,638 |
Note: In this estimate we have taken general specification of construction work, however, if you want to change the specification by providing good quality marble floor or ceramic tile floor, Teakwood in door and windows, the cost will increase and you can find estimated cost by using cost estimator given at the link below.
Cost Estimator>>
|
|
| | Files attached : No files |
|
|
|
| | Answered by S L Gupta on Tue Jun 10, 2008 1:35 PM | |
The area given by your good self is 150 sq. yards or 1350 Sq. feet. You want to construct double storey house but did not mention the area for second storey or first floor level.
Considering area of second storey 90 % of the ground floor area that is equal to 1215 sq. feet, the total area will be equal to 1350 +1215 = 2565 sq. feet. The cost of construction of a house depends on the specification used for construction work.
Tentative estimated cost is:
S.No. |
Nature of work |
Amount in Rupees |
1 |
Earth work Excavation in foundation & earth filling under floor |
41,040 |
2 |
Cement concrete in foundation 1:8:16 |
47,787 |
3 |
Brick work in cement mortar 1:6 in foundation work |
45,015 |
4 |
D P C |
14,765 |
5 |
Brick work in cement mortar 1:6 in super structure |
1,07,152 |
6 |
Tile tracing in roof |
52,639 |
7 |
Rain water pipe |
12,826 |
8 |
RCC without steel in ratio of 1:2:4 |
1,73,933 |
9 |
M S Steel for RCC |
2,17,512 |
10 |
Makrana dungri stone flooring |
1,99,974 |
11 |
Plastering on ceiling |
14,596 |
12 |
Plastering on walls |
31,679 |
13 |
Cement pointing |
9,029 |
14 |
Glaze tiles on walls in bathroom and Kitchen |
70,568 |
15 |
Hard wood frame for door and windows |
1,01,574 |
16 |
Hard wood door shutters |
81,181 |
17 |
Hard wood window shutters |
40,395 |
18 |
Hard wood cupboard box type |
66,918 |
19 |
Iron grills |
28,915 |
20 |
Painting or spirit polishing on wood work |
15,903 |
21 |
White washing on ceiling |
3,771 |
22 |
Oil bond distemper on walls |
56,020 |
23 |
Snowcem for exterior walls |
6,413 |
|
Total Rs. |
14, 38,910 |
|
Electrical fittings including wiring @ 10% of total cost |
1,43,891 |
|
Water Supply & sanitary fitting @10% of total cost |
1,43,891 |
|
Sewerage @ 5% of total cost |
71,946 |
|
Grand Total |
17,98,638 |
Note: In this estimate we have taken general specification of construction work, however, if you want to change the specification by providing good quality marble floor or ceramic tile floor, Teakwood in door and windows, the cost will increase and you can find estimated cost by using cost estimator given at the link below.
Cost Estimator>>
|
|
| | Files attached : No files |
|
|
|
| | Locked by S L Gupta on Fri Jun 06, 2008 12:09 PM |
|
|
|
|
|
|
|