|
Question details | |
|
|
| what is material quantity for brick work using cement mortar 1:5, wall area 100 sq. ft. and how it is calculated
Price : Rs.0 Paid : Rs.0 Balance : Rs.0 Question category : Brick work On : 05/26/2008 Views : 11353 Status : Closed Files attached : No files Expert(s) chosen: No experts |
| |
|
| |
| |
|
Status history |
|
| | Answered by Mohini Sharma on Wed May 14, 2008 5:46 PM | | Hello Vijay Kumar Verma,
The details given below for calculating different material are used in brick work.
S. No. Brick work Quantity Cement Sand Bricks 1 With cement mortar 1:3 1 cubic meter 2.4 bags .25 cum 480 no. 2 With cement mortar 1:4 1 cubic meter 1.75 bags .25 cum 480 no. 3 With cement mortar 1:5 1 cubic meter 1.45 bags .26 cum 480 no. 4 With Cement mortar 1:6 1 cubic meter 1.20 bags .26 cum 480 no. 5 With cement mortar 1:7 1 cubic meter 1 bag .26 cum 480 no.
You have given only area of the wall without giving thickness of the wall for calculating the materials in brick work. Assuming 9 inch thick wall, the calculation of material is following.
• Volume of brick work= area of wall X thickness of wall = 100 X 9/12 = 75 cft or 2.12 cum • Cement = 2.12 X 1.45 = 3.07 bags • Sand = 2.12 X .26 = 0.55 cum • Bricks = 2.12 X 480 = 1017 no.
Thanks. |
|
| | Files attached : No files |
|
|
|
|
|
|
|
Copyright 2007- GharExpert.com All rights reserved.
|