Question details | |
|
|
| for electrical wiring ,when should start?which company is good(cables)?what r the good main swicthes?
Price : Rs.0 Paid : Rs.0 Balance : Rs.0 Question category : Interior Lighting On : 05/01/2008 Views : 2005 Status : Closed Files attached : No files Expert(s) chosen: No experts |
| |
|
| |
| |
|
Status history |
|
| | Answered by Mohini Sharma on Thu May 01, 2008 3:44 PM | | Hey
1) Electrical conduit pipe, fan hook, light point should be laid at the time of laying RCC slab. 2) All electrical boxes, electrical conduit pipes and other points should be fixed into the wall before plastering. 3) Electrical wiring should be done when the plaster is dried before starting painting and white washing. 4) You should use good quality ISI mark best material (best quality cable and switches) available in the market and should be purchased from reputed firms.
Thanks |
|