| Mr. Sunil,
As desired by your good self the detail cost estimate for construction of your house as per drawing supplied by you from 1st story to 3rd story with mumty at 4th story for Rs. 7,479,52 is hereby sent to you. The stage wise details of materials required for the construction work is also attached. This will help you to budget properly and you can arrange construction material accordingly. Please let me know if you have any question?
DETAIL ESTIMATES FOR CONSTRUCTION OF A HOUSE OF SHRI SUNIL VANUGOPAL ,ROHINI AT DELHI AS PER DRAWING SUPPLIED
DETAIL ESTIMATES FOR CONSTRUCTION OF A HOUSE OF SHRI SUNIL VANUGOPAL ,ROHINI AT DELHI AS PER DRAWING SUPPLIED |
Sr.No |
Quantity |
Description of item |
Rate |
Unit |
Amount |
1 |
25.999 |
Earth work in excavation in foundation and plinth including refilling around the masonry complete |
55 |
CUM |
1,430 |
2 |
16 |
Earth work in filling under floors including carriage from 10 km including watering ramming complete |
100 |
CUM |
1,600 |
3 |
8.66 |
Cement concrete 1:8 :16 in foundation and plinth with brick ballast 40 mm gauze |
1450 |
CUM |
12,557 |
4 |
10.81 |
First class brick work in cement mortar 1:6 in foundation and plinth complete |
1810 |
CUM |
19,566 |
5 |
5.69 |
40 mm Thick horizontal damp proof course with cement concrete1:2:4 and two coat of hot bitumen complete |
170 |
SQM |
967 |
6 |
|
First class brick work in cement mortar 1:4 in super structure |
|
|
0 |
a |
12.62 |
First story |
1890 |
CUM |
18,804 |
b |
13.67 |
Second story |
1950 |
CUM |
26,657 |
c) |
13.67 |
Third story |
2020 |
CUM |
27,613 |
d |
7.05 |
4 th sstoory |
2100 |
CUM |
14,805 |
7 |
|
11.43 cm thick brick wall in cement mortar 1:4 in super structure |
|
|
0 |
a |
24.93 |
First story |
250 |
SQM |
6,233 |
b |
16.1 |
Second story |
260 |
SQM |
4,186 |
c) |
16.1 |
Third story |
270 |
SQM |
4,347 |
8 |
|
RCC 1:1.5:3 in lintels , beams , columns including centering and shuttering but excluding steel reinforcement complete in position |
|
|
0 |
a |
1.6 |
First story |
5100 |
CUM |
8,160 |
b |
1.62 |
Second story |
5150 |
CUM |
8,343 |
c) |
1.62 |
Third story |
5200 |
CUM |
8,424 |
9 |
|
RCC 1:1.5:3 in slabs including centering and shuttering but excluding steel reinforcement complete in position |
|
|
0 |
a |
3.21 |
First story |
5050 |
CUM |
16,211 |
b |
3.21 |
Second story |
5100 |
CUM |
16,371 |
c) |
3.21 |
Third story |
5200 |
CUM |
16,692 |
d |
0.45 |
4th story |
5250 |
CUM |
2,363 |
10 |
6 |
AC band 100 mm diameter |
50 |
each |
300 |
11 |
|
Supply of AC PIPES in cluding fixing in floors and walls complete |
|
|
0 |
a |
26 |
100 mm Diameter |
120 |
Meter |
3,120 |
b |
15 |
75 mm diameter |
100 |
Meter |
1,500 |
c) |
10 |
150 mm diameter |
200 |
Meter |
2,000 |
12 |
22.12 |
Tile terracing with bricks tiles 9 " X4.5" X1.5 " on mud mortar laid on earth filling 3 inch thick on bitumen painted RCC surface complete |
234 |
sqm |
5,176 |
13 |
|
12 mm Thick cement plaster 1:4 under ceiling /roof |
|
|
0 |
a |
28.42 |
First story |
65 |
sqm |
1,847 |
b |
28.42 |
Second story |
66 |
sqm |
1,876 |
c) |
28.42 |
Third story |
67 |
sqm |
1,904 |
d |
4.05 |
4th story |
68 |
sqm |
275 |
14 |
|
15 mm thick cement plaster 1:4 on brick walls complete |
|
|
0 |
a |
159.32 |
First story |
67 |
sqm |
10,674 |
b |
151.7 |
Second story |
68 |
sqm |
10,316 |
c) |
151.7 |
Third story |
69 |
sqm |
10,467 |
d |
63.58 |
4th story |
70 |
sqm |
4,451 |
15 |
25.75 |
Base course of floors consisting of 100 mm thick cement concrete 1:8:16 with brick ballast 40 mm gauze |
180 |
sqm |
4,635 |
16 |
|
Secreed 50 mm thick with cement concrete 1:8:16 on slab. |
|
|
0 |
a |
18 |
Second story |
90 |
Sqm |
1,620 |
b |
18 |
Third story |
91 |
Sqm |
1,638 |
17 |
91.77 |
White Marble Stone Flooring laid with 20 mm thick cement mortar 1:3 including filling the joints with white cement and rubbed and poliished complete |
1100 |
Sqm |
100,947 |
18 |
50.52 |
Glaze tiles /ceramic tiles fixed on walls with 12 mm thick cement mortar 1:3 including filling the joints with white cement mixed with pigment according to the required colour and size complete |
520 |
sqm |
26,270 |
19 |
0.72 |
Grenite marble stone slab laid with 20 mm thick cement mortar 1:3 including filling the joints with white cement rubbed and polished com -lete |
1500 |
sqm |
1,080 |
20 |
1.17 |
Hardwood frames for doors and windows completely including fixing with iron holdfast and cement concrete 1:2:4 complete |
32500 |
cum |
38,025 |
21 |
20 |
Hard wood door shutter with teak phase ply on both side fixed in position |
1300 |
sqm |
26,000 |
22 |
13.07 |
Hard wood windows shutters with glass panels fixed in position |
1080 |
sqm |
14,116 |
23 |
23.27 |
Hard wood door and windows wiregauze shutters fixed in position |
1000 |
sqm |
23,270 |
24 |
43.209 |
20 mm thick ply board fixed in position for cup boards complete |
520 |
sqm |
22,469 |
25 |
13.2 |
Fixing sunmika on cup board shutters including necessary nails etc. |
300 |
sqm |
3,960 |
26 |
14.89 |
Mild steel tor /ribbed bars for RCC including bending binding and placing |
5100 |
qtl. |
75,939 |
27 |
4.708 |
Mild steel grills ,railing completely fixed in position |
5100 |
qtl. |
24,011 |
28 |
|
Door and windows fittings completely fixed with screws etc. |
|
|
0 |
a |
6 |
Mortice locks & latches |
350 |
each |
2,100 |
b |
38 |
Handles 6 inches |
10 |
each |
380 |
c) |
25 |
Tower bolt 10 inches |
15 |
each |
375 |
d |
25 |
Tower bolt 6 inches |
12 |
each |
300 |
e |
13 |
Sliding bolt |
40 |
each |
520 |
f |
56 |
Handle 4 inches |
8 |
each |
448 |
g |
112 |
Tower bolt 4 inches |
8 |
each |
896 |
h |
19 |
Door stoper |
10 |
each |
190 |
i |
6 |
Helical door spring |
250 |
each |
1,500 |
j |
30 |
Cupboard handle |
10 |
each |
300 |
k |
30 |
Megnet for cupboard |
8 |
each |
240 |
l |
9 |
Cupboard locks |
50 |
each |
450 |
29 |
|
Water supply and sanitary items |
|
|
0 |
a |
1 |
Sink |
500 |
each |
500 |
b |
3 |
Wash basin |
500 |
each |
1,500 |
c) |
3 |
Shower |
100 |
each |
300 |
d |
3 |
Consealed |
100 |
each |
300 |
e |
18 |
Bibcock long bodoy |
150 |
each |
2,700 |
f |
3 |
Bibcock short body |
100 |
each |
300 |
g |
1 |
Water closet Indian |
500 |
each |
500 |
h |
2 |
Water closet English |
800 |
each |
1,600 |
i |
2 |
Waste pipe |
20 |
each |
40 |
j |
2 |
Jet |
50 |
each |
100 |
k |
2 |
Paper holder |
100 |
each |
200 |
L |
50 |
G I Pipe with accessaries |
80 |
Meter |
4,000 |
m |
3 |
Sstop cock |
200 |
each |
600 |
N |
2 |
Water tank 500 liter |
1500 |
each |
3,000 |
30 |
141.01 |
Painting two coat including priming coat on wood work complete |
35 |
sqm |
4,935 |
31 |
615.62 |
Painting two coat inluding priming coat on walls |
30 |
sqm |
18,469 |
32 |
Job |
Electrical fittings including laying pipes ,fan hooks ,ceiling rose ,boxes seats ,switches and other accessaries |
|
Total |
679,957 |
|
|
|
10% |
|
67,995 |
|
|
|
|
G.Total |
747,952 |
DETAILS OF VARIOUS MATERIALS UP TO PLINTH LEVEL/ DPC Cement = 23 Bags Fine sand = 200. CFT Coarse Sand = 150 CFT Brick ballast= 250 cft Bricks = 5000. Nos. Bitumen = 20 Kg.
UP TO FIRST STORY Cement = 110 Bags Fine sand =200cft Coarse Sand = 300 cft Brick ballast =80 cft Bricks =7200 Nos. Marble stone =350 sft Glaze tiles = 230 sft Garenite stone= 8 sft Frames for door and windows=140 rft Door shutters= 4 Nos. Wiundows shutters =12 Nos. Wiregauze door shutters =2 Nos. Mild steel bars = 5.2 qtl. AC band 100 mm diameter = 6 Nos. AC PIPES 100 MM diameter= 10 meter A C pipe 75 mm diameter = 5 meter Bizari = 160 cft G I Pipe = 20 Meter AC pipe 150 mm diameter =10 Meter
SECOND STORY Cement = 110 bags Fine Sand = 200 cft Coarse Sand = 280 cft. Brick ballast = 35 cft. Bricks = 7000. Nos. Bizari = 160 cft. Marble stone =320 sft. Glaze tiles = 180 sft. Door & window frames = 140 rft. Doors shutters = 4 Nos. Window shutters = 20 Nos. Door shutters wiregauze = 2 Nos. Mild steel Bars = 4.84 Qtl. AC pipe 100 mm diameter = 8 meter AC pipe 75 mm diameter = 5 meter G I Pipe = 15 Meter
THIRD STORY Same as in second story
FOURTH STORY Cement = 25 Bags Fine Sand = 100 Cft. Coarse Sand = 100 Cft. Bizari = 20 Cft. Door frames = 16 Rft. Door shutter = I Nos. Bricks = 3000 Nos. Bricks Tiles = 800 Nos.
At the time of finishing Ply Board = 450 sft. Sunmica = 140 Sft. Grills Mild steel for windows = 4.7 Qtl. Paint = 60 litre Door and window fittings Latch locks /Mortice Locks =6 Nos Handle 6 Inch = 38 Nos. T.Bat 10" = 25 Nos. T.Bat 6" = 25 Nos. Sliding Bolt = 13 Nos. Handle 4 Inch = 56 Nos. T.Bat 6" = 112 Nos. Door stopper = 19 Nos. Helical door spring = 6 Nos. C B Handle = 30 Nos. Megnet = 30 Nos. C B Locks = 9 Nos. Water supply and drainage fittings Sink = 1 Nos. W.B.= 3 Nos. Shower= 3 Nos. Concealed = 3 Nos. Long body = 18 Nos. Short Body = 3 Nos. Water closet Indian = 1 Nos. W.C.English type = 2 Nos. Waste Pipe -= 3 Nos. Jet = 2 Nos. Paper holder = 2 Nos. Stop cocks = 3 Nos. Water Tank 500 litre = 2 Nos.
Thanks |