Sat Nov 14, 2015 | Post #1 | JAI PRAKASH
Join date: May 2014 | Total TMT Bars - 1.8 tonne Total Cement - 200 bags Bricks - 80k Dust - 400 ft. Reti - 200 ft. Rodi - 400 ft.
This is not exact as that can be finalized after the layout.
| |
|
Tue Nov 17, 2015 | Post #2 | raj
Join date: Nov 2015 | Thanks Jai | |
|
Tue Nov 17, 2015 | Post #3 | JAI PRAKASH
Join date: May 2014 | Welcome sir.
| |
|
Wed Feb 15, 2017 | Post #4 | Malek moin
Join date: Feb 2017 | Post subject: Estimate
Dear Sir, I am planning to construct of ground floor 14' x 35'.Total 490 square feet. May I know the quantity of steel(16/12/10/8/6 mm), sand, no. bricks, cement bags and other.
Thank you Malek. Moin | |
|
Thu Feb 16, 2017 | Post #5 | S L Gupta (Civil Engg)
Join date: Mar 2008 | Dear Sir, use estimator at the website gharexpert. com link given below
http://www.gharexpert.com/Estimator/Startpage.aspx
| |
|
|